Task #1295
closed
- Status changed from New to In Progress
- % Done changed from 0 to 50
- % Done changed from 50 to 70
70% include the implementation of staged 1 & 2.
Should I move forward and implement 3rd stage even though we use the temporary certificates? If so, any hint on how to load the default user identity?
You should upload stage 1 and 2 code for review.
- Status changed from In Progress to Code review
- % Done changed from 70 to 100
Should I leave this task open until we'll have an updated spec?
- Status changed from Code review to Closed
This task can close when current spec is implemented, and code is merged.
If spec is later updated, this task can reopen as Status=Feedback, or a new task can be created.